Second trial run underway for electricity supply from Rooppur to national grid
businessnews24bd.com
The Rooppur Nuclear Power Plant in Ishwardi upazila of Pabna district, has started supplying electricity to the national grid for the second time on a trial basis on Monday.
Dr Md Kabir Hossain, project director of the Rooppur Nuclear Power Plant construction project, said around 300-350 megawatts of electricity would be supplied to the national grid on a trial basis for 10 to 24 hours during this second phase.
Various technical tests will be conducted during this period to assess the plant's power generation system and its integrated operation with the national grid, he said.
Earlier, the plant began its first trial supply to the national grid on November 17.
During the initial phase, the first unit generated up to 375MW of electricity and supplied it to the grid for around eight and a half hours.
The estimated market value of the electricity supplied during that period was around Tk 2 crore. The grid connection was subsequently disconnected at 11:50pm.
Dr Md Zahedul Hasan, managing director of Nuclear Power Plant Company Bangladesh Limited (NPCBL), said the performance and stability of the turbine, generator and integrated operating system with the national grid were closely monitored during the first grid connection.
As the test results were satisfactory, the unit was reconnected to the grid for the second phase after a necessary break, he said.
"After several hours of monitoring during the second phase, the grid connection will be disconnected based on an overall assessment of the situation. Power generation will be increased or reduced as required during subsequent tests," he said.
The unit might also need to be temporarily shut down for certain tests, he added.
Power Grid Bangladesh PLC (PGB) will take necessary measures to maintain grid balance in line with fluctuations in electricity generation, he said.
Praising the efforts of NPCBL engineers, scientists, officials and employees, the managing director said they were making every effort to supply electricity from the first unit to the national grid at full capacity before the next summer, between February and March 2027.
He expressed hope that the unit would be able to supply around 1,150MW at that stage, significantly helping reduce the country's power shortage during the coming summer.
Project officials said grid connection was an important technical step in establishing coordination between the power plant's generation system and the national transmission network.
However, they clarified that the start of trial electricity supply did not mean the plant had entered full commercial operation.
Generation capacity will be increased gradually in line with the guidelines of the International Atomic Energy Agency (IAEA) and international nuclear safety standards.
The first unit is expected to reach 100 percent of its generation capacity in phases after completion of the required tests and obtaining licences and regulatory approvals.
The Rooppur Nuclear Power Plant is being built with two units, each having a generation capacity of 1,200MW. Once both units become operational, the plant will have a combined capacity of 2,400MW.
The second phase of trial power supply is being viewed as another significant step forward in Bangladesh's journey towards nuclear power generation.